Garage, Inc., has identified the following two mutually exclusive projects:
Explanation: a.
b.
c.
Year | Cash Flow (A) | Cash Flow (B) | |||||
0 | –$ | 29,900 | –$ | 29,900 | |||
1 | 15,300 | 4,750 | |||||
2 | 13,200 | 10,250 | |||||
3 | 9,650 | 16,100 | |||||
4 | 5,550 | 17,700 | |||||
a-1 |
What is the IRR for each of these projects? (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16))
|
IRR | ||
Project A | % | |
Project B | % | |
a-2 |
Using the IRR decision rule, which project should the company accept?
|
Project A |
a-3 | Is this decision necessarily correct? |
No |
b-1 |
If the required return is 11 percent, what is the NPV for each of these projects? (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16))
|
NPV | ||
Project A | $ | |
Project B | $ | |
b-2 | Which project will the company choose if it applies the NPV decision rule? |
Project B |
c. |
At what discount rate would the company be indifferent between these two projects? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))
|
Discount rate | % |
Explanation: a.
The IRR is the interest rate that makes the NPV of the project equal to zero. The equation for the IRR of Project A is:
|
0 = –$29,900 + $15,300 / (1 + IRR) + $13,200 / (1 + IRR)2 + $9,650 / (1 + IRR)3 + $5,550 / (1 + IRR)4
|
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that: |
IRR = 20.57% |
The equation for the IRR of Project B is |
0 = –$29,900 + $4,750 / (1 + IRR) + $10,250 / (1 + IRR)2 + $16,100 / (1 + IRR)3 + $17,700 / (1 + IRR)4
|
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that: |
IRR = 18.58% |
Examining the IRRs of the projects, we see that the IRRA is greater than the IRRB,
so IRR decision rule implies accepting project A. This may not be a
correct decision; however, because the IRR criterion has a ranking
problem for mutually exclusive projects. To see if the IRR decision rule
is correct or not, we need to evaluate the project NPVs.
|
b.
The NPV of Project A is: |
NPVA = –$29,900 + $15,300 / 1.11 + $13,200 / 1.112 + $9,650 / 1.113 + $5,550 / 1.114 |
NPVA = $5,309.15 |
And the NPV of Project B is: |
NPVB = –$29,900 + $4,750 / 1.11 + $10,250 / 1.112 + $16,100 / 1.113 + $17,700 / 1.114 |
NPVB = $6,130.13 |
The NPVB is greater than the NPVA, so we should accept Project B. |
c.
To
find the crossover rate, we subtract the cash flows from one project
from the cash flows of the other project. Here, we will subtract the
cash flows for Project B from the cash flows of Project A. Once we find
these differential cash flows, we find the IRR. The equation for the
crossover rate is:
|
Crossover rate: 0 = $10,550 / (1 + R) + $2,950 / (1 + R)2 – $6,450 / (1 + R)3 – $12,150 / (1 + R)4 |
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that: |
R = 14.09% |
At
discount rates above 14.09 percent choose project A; for discount rates
below 14.09 percent choose project B; indifferent between A and B at a
discount rate of 14.09 percent.
|
Calculator Solution: |
Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. |
Project A | ||||
CFo
| –$29,900 |
CFo
| –$29,900 | |
C01
| $15,300 |
C01
| $15,300 | |
F01
| 1 |
F01
| 1 | |
C02
| $13,200 |
C02
| $13,200 | |
F02
| 1 |
F02
| 1 | |
C03
| $9,650 |
C03
| $9,650 | |
F03
| 1 |
F03
| 1 | |
C04
| $5,550 |
C04
| $5,550 | |
F04
| 1 |
F04
| 1 | |
IRR CPT | I = 11% | |||
20.57% | NPV CPT | |||
$5,309.15 |
Project B | ||||
CFo
| –$29,900 |
CFo
| –$29,900 | |
C01
| $4,750 |
C01
| $4,750 | |
F01
| 1 |
F01
| 1 | |
C02
| $10,250 |
C02
| $10,250 | |
F02
| 1 |
F02
| 1 | |
C03
| $16,100 |
C03
| $16,100 | |
F03
| 1 |
F03
| 1 | |
C04
| $17,700 |
C04
| $17,700 | |
F04
| 1 |
F04
| 1 | |
IRR CPT | I = 11% | |||
18.58% | NPV CPT | |||
$6,130.13 |
Crossover rate | ||
CFo | $0 | |
C01 | $10,550 | |
F01 | 1 | |
C02 | $2,950 | |
F02 | 1 | |
C03 | –$6,450 | |
F03 | 1 | |
CO4 | –$12,150 | |
FO4 | 1 | |
IRR CPT | ||
14.09% |
No comments:
Post a Comment