Brady
Construction Company contracted to build an apartment complex for a
price of $5,000,000. Construction began in 2013 and was completed in
2015. The following are a series of independent situations, numbered 1
through 6, involving differing costs for the project. All costs are
stated in thousands of dollars.
| Estimated Costs to Complete | ||||||||||||
| Costs Incurred During Year | (As of the End of the Year) | |||||||||||
| Situation | 2013 | 2014 | 2015 | 2013 | 2014 | 2015 | ||||||
| 1 | 1,500 | 2,100 | 900 | 3,000 | 900 | — | ||||||
| 2 | 1,500 | 900 | 2,400 | 3,000 | 2,400 | — | ||||||
| 3 | 1,500 | 2,100 | 1,600 | 3,000 | 1,500 | — | ||||||
| 4 | 500 | 3,000 | 1,000 | 3,500 | 875 | — | ||||||
| 5 | 500 | 3,000 | 1,300 | 3,500 | 1,500 | — | ||||||
| 6 | 500 | 3,000 | 1,800 | 4,600 | 1,700 | — | ||||||
| | ||||||||||||