Consider the following two mutually exclusive projects:
Explanation: a.
b.
c.
d.
e.
f.
Year | Cash Flow (A) | Cash Flow (B) | |||||
0 | –$ | 348,000 | –$ | 51,000 | |||
1 | 47,000 | 24,200 | |||||
2 | 67,000 | 22,200 | |||||
3 | 67,000 | 19,700 | |||||
4 | 442,000 | 14,800 | |||||
Whichever project you choose, if any, you require a 14 percent return on your investment. |
a-1 |
What is the payback period for each project? (Round your answers to 2 decimal places. (e.g., 32.16))
|
Payback period | ||
Project A | years | |
Project B | years | |
a-2 | If you apply the payback criterion, which investment will you choose? |
Project B |
b-1 |
What is the discounted payback period for each project? (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16))
|
Discounted payback period | ||
Project A | years | |
Project B | years | |
b-2 | If you apply the discounted payback criterion, which investment will you choose? |
Project B |
c-1 |
What is the NPV for each project? (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16))
|
NPV | ||
Project A | $ | |
Project B | $ | |
c-2 | If you apply the NPV criterion, which investment will you choose? |
Project A |
d-1 |
What is the IRR for each project? (Round your answers to 2 decimal places. (e.g., 32.16))
|
IRR | ||
Project A | % | |
Project B | % | |
d-2 | If you apply the IRR criterion, which investment will you choose? |
Project B |
e-1 |
What is the profitability index for each project? (Do not round intermediate calculations and round your final answers to 3 decimal places. (e.g., 32.161))
|
Profitability index | ||
Project A | ||
Project B | ||
e-2 | If you apply the profitability index criterion, which investment will you choose? |
Project B |
f | Based on your answers in (a) through (e), which project will you finally choose? |
Project A |
Explanation: a.
The payback period for each project is: | |
A: | 3 + ($167,000/$442,000) = 3.38 years |
B: | 2 + ($4,600/$19,700) = 2.23 years |
The payback criterion implies accepting Project B, because it pays back sooner than project A. |
b.
The discounted payback for each project is: | |
A: | $47,000/1.14 + $67,000/1.142 + $67,000/1.143 = $138,005.49 |
$442,000/1.144 = $261,699.48 | |
Discounted payback = 3 + ($348,000 – 138,005.49)/$261,699.48 = 3.80 years | |
B: | $24,200/1.14 + $22,200/1.142 = $38,310.25 |
$19,700/1.143 = $13,296.94 | |
Discounted payback = 2 + ($51,000 – 38,310.25)/$13,296.94 = 2.95 years | |
The discounted payback criterion implies accepting Project B because it pays back sooner than A. |
c.
The NPV for each project is: | |
A: | NPV = –$348,000 + $47,000/1.14 + $67,000/1.142 + $67,000/1.143 + $442,000/1.144 |
NPV = $51,704.97 | |
B: | NPV = –$51,000 + $24,200/1.14 + $22,200/1.142 + $19,700/1.143 + $14,800/1.144 |
NPV = $9,369.98 | |
NPV criterion implies we accept project A because project A has a higher NPV than project B. |
d.
The IRR for each project is: | |
A: | $348,000 = $47,000/(1+IRR) + $67,000/(1+IRR)2 + $67,000/(1+IRR)3 + $442,000/(1+IRR)4 |
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that: | |
IRR = 18.89% | |
B: | $51,000 = $24,200/(1+IRR) + $22,200/(1+IRR)2 + $19,700/(1+IRR)3 + $14,800/(1+IRR)4 |
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that: | |
IRR = 23.47% | |
IRR decision rule implies we accept Project B because IRR for B is greater than IRR for A. |
e.
The profitability index for each project is: | |
A: | PI = ($47,000/1.14 + $67,000/1.142 + $67,000/1.143 + $442,000/1.144) / $348,000 = 1.149 |
B: | PI = ($24,200/1.14 + $22,200/1.142 + $19,700/1.143 + $14,800/1.144) / $51,000 = 1.184 |
Profitability index criterion implies accept Project B because its PI is greater than Project A’s. |
Calculator Solution: |
Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. |
CF(A) | c. | d. | e. | |||
CFo
| –$348,000 |
CFo
| –$348,000 |
CFo
| $0 | |
C01
| $47,000 |
C01
| $47,000 |
C01
| $47,000 | |
F01
| 1 |
F01
| 1 |
F01
| 1 | |
C02
| $67,000 |
C02
| $67,000 |
C02
| $67,000 | |
F02
| 2 |
F02
| 2 |
F02
| 2 | |
C03
| $442,000 |
C03
| $442,000 |
C03
| $442,000 | |
F03
| 1 |
F03
| 1 |
F03
| 1 | |
I = 14% | IRR CPT | I = 14% | ||||
NPV CPT | 18.89% | NPV CPT | ||||
$51,704.97 | $399,704.97 |
PI = $399,704.97 / $348,000 = 1.149 |
CF(B) | c. | d. | e. | |||
CFo
| –$51,000 |
CFo
| –$51,000 |
CFo
| $0 | |
C01
| $24,200 |
C01
| $24,200 |
C01
| $24,200 | |
F01
| 1 |
F01
| 1 |
F01
| 1 | |
C02
| $22,200 |
C02
| $22,200 |
C02
| $22,200 | |
F02
| 1 |
F02
| 1 |
F02
| 1 | |
C03
| $19,700 |
C03
| $19,700 |
C03
| $19,700 | |
F03
| 1 |
F03
| 1 |
F03
| 1 | |
C04
| $14,800 |
C04
| $14,800 |
C04
| $14,800 | |
F04
| 1 |
F04
| 1 |
F04
| 1 | |
I = 14% | IRR CPT | I = 14% | ||||
NPV CPT | 23.47% | NPV CPT | ||||
$9,369.98 | $60,369.98 |
PI = $60,369.98 / $51,000 = 1.184 |
f.
The final decision should be based on the NPV since it does not have the ranking problem associated with the other capital budgeting techniques. |
No comments:
Post a Comment