Problem 8-9 Calculating NPV [LO 4]
Year | Cash Flow |
0 | | –$ | 32,000 |
1 | | | 14,200 | |
2 | | | 17,500 | |
3 | | | 11,600 | |
|
Requirement 1: |
What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations.)
Requirement 2: |
What is the NPV at a discount rate of 10 percent? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)
|
Requirement 3: |
What is the NPV at a discount rate of 20 percent? (Do not round intermediate calculations. Negative amount should be indicated by a minus sign.Round your answer to 2 decimal places (e.g., 32.16).)
|
Requirement 4: |
What is the NPV at a discount rate of 30 percent? (Do not round intermediate calculations. Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places (e.g., 32.16).)
|
Explanation:
1: |
The
NPV of a project is the PV of the outflows plus the PV of the inflows.
At a zero discount rate (and only at a zero discount rate), the cash
flows can be added together across time. So, the NPV of the project at a
zero percent required return is:
|
|
NPV = – $32,000 + 14,200 + 17,500 + 11,600 |
NPV = $11,300 |
|
2: |
The NPV at a 10 percent required return is: |
|
NPV = – $32,000 + $14,200 / 1.10 + $17,500 / 1.102 + $11,600 / 1.103 |
NPV = $4,087.15 |
|
3: |
The NPV at a 20 percent required return is: |
|
NPV = – $32,000 + $14,200 / 1.20 + $17,500 / 1.202 + $11,600 / 1.203 |
NPV = –$1,300.93 |
|
4: |
And the NPV at a 30 percent required return is: |
|
NPV = – $32,000 + $14,200 / 1.30 + $17,500 / 1.302 + $11,600 / 1.303 |
NPV = – $5,441.97 |
|
Notice
that as the required return increases, the NPV of the project
decreases. This will always be true for projects with conventional cash
flows. Conventional cash flows are negative at the beginning of the
project and positive throughout the rest of the project.
|
Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. |
CFo
| –$32,000 |
CFo
| –$32,000 |
C01
| $14,200 |
C01
| $14,200 |
F01
| 1 |
F01
| 1 |
C02
| $17,500 |
C02
| $17,500 |
F02
| 1 |
F02
| 1 |
C03
| $11,600 |
C03
| $11,600 |
F03
| 1 |
F03
| 1 |
I = 0% | I = 10% |
NPV CPT | NPV CPT |
$11,300.00 | $4,087.15 |
CFo
| –$32,000 |
CFo
| –$32,000 |
C01
| $14,200 |
C01
| $14,200 |
F01
| 1 |
F01
| 1 |
C02
| $17,500 |
C02
| $17,500 |
F02
| 1 |
F02
| 1 |
C03
| $11,600 |
C03
| $11,600 |
F03
| 1 |
F03
| 1 |
I = 20% | I = 30% |
NPV CPT | NPV CPT |
–$1,300.93 | –$5,441.97 |
|
No comments:
Post a Comment