The following materials standards have been established for a particular product:
Standard quantity per unit of output …………….. 3.3 hours
Standard price ……………………………………. $16.15 per hour
The following data pertain to operations concerning the product for the last month:
Actual hours worked ………………….. 6,300 hours
Actual total labor cost ………….. $103,635
Actual output ……………………………….. 2,000 units
What is the labor rate variance for the month?
Answer
$1,890 U
Standard quantity per unit of output …………….. 3.3 hours
Standard price ……………………………………. $16.15 per hour
The following data pertain to operations concerning the product for the last month:
Actual hours worked ………………….. 6,300 hours
Actual total labor cost ………….. $103,635
Actual output ……………………………….. 2,000 units
What is the labor rate variance for the month?
$2,955 F |
|
$2,955 U |
|
$1,890 U |
|
$4,935 F |
Answer
$1,890 U