On June 15, 2013, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C. for $220 million. The expected completion date is April 1 of 2015, just in time for the 2015 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):

On June 15, 2013, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C. for $220 million. The expected completion date is April 1 of 2015, just in time for the 2015 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):

  2013 2014 2015
  Costs incurred during the year $ 40   $ 80   $ 50  
  Estimated costs to complete as of 12/31   120     60      


Required: