The Koski Company has established standards as follows: Direct material 3.00 pounds @ $5.50/pound = $16.50 per unit Direct labor 2.10 hours @ $9.50/hour = $19.95 per unit Variable overhead 2.10 hours @ $6.50/hour = $13.65 per unit Actual production figures for the past year were as follows: Units produced 650 Direct materials used 2,540 pounds Direct materials purchased (4,500 pounds) $25,200 Direct labor cost (1,100 hours) $10,670 Variable overhead cost incurred $7,040 The materials quantity variance is: (Round your answer to nearest dollar amount.) $10,725 U $3,304 F $3,304 U $3,245 U

The Koski Company has established standards as follows:

  Direct material
 3.00 pounds @ $5.50/pound = $16.50 per unit
  Direct labor
 2.10 hours @ $9.50/hour = $19.95 per unit
  Variable overhead
 2.10 hours @ $6.50/hour = $13.65 per unit

Actual production figures for the past year were as follows:

  Units produced
 650               
  Direct materials used
 2,540 pounds  
  Direct materials purchased (4,500 pounds)
$25,200               
  Direct labor cost (1,100 hours)
$10,670               
  Variable overhead cost incurred
$7,040        

The materials quantity variance is: (Round your answer to nearest dollar amount.)

$10,725 U
$3,304 F
$3,304 U
$3,245 U
Answer
$3,245 U